CalvertHealth Medical Center Expansion Updates

CalvertHealth Medical Center Expansion Updates

Here's what to expect in the coming weeks:

The interior framing is taking place on all floors as well as the plumbing and HVAC ductwork. The roof installation is complete and the exterior brickwork is about 3/4 done.

Work on the tower is expected to be complete in March 2019.

A few reminders:

  • The Emergency Department entrance is now the main entrance to CalvertHealth Medical Center.
  • Complimentary valet parking is available to patients and guests in front of the Medical Office Building M-F, 9 a.m.-2 p.m.
  • Volunteers are located by the Emergency Department entrance (directly across from the ED registration desk) to assist patients and visitors.
  • Same Day Surgery patients register/check-in at the Cardiopulmonary Department. A temporary waiting area for Same Day Surgery patients and visitors is located by the elevators.
  • The front exit from Same Day Surgery is available for patient pick-up only.
  • The Gift Shop has been relocated to the medical center basement.
Thank you for your continued patience and cooperation during construction.